Morven Hawthorn Pit Grid Connection Project

The Morven Hawthorn Pit Grid Connection Project consists of onshore and offshore infrastructure associated with the transmission of electricity generated by either Morven North or Morven South to the national grid.

It includes underwater offshore and underground onshore electricity cables and a land substation.

Two people discussing a large map on a table indoors

The Secretary of State for the Department of Energy Security and Net Zero (DESNZ) has directed that the offshore and onshore elements of the Morven Hawthorn Pit Grid Connection Project that are within England should be consented via a Development Consent Order (DCO) under the Planning Act 2008.

For the section of the Morven Hawthorn Pit Grid Connection Project within Scottish waters, we will apply to the Scottish Government’s Marine Directorate for a Marine Licence under the Marine and Coastal Access Act 2009.

Consultation

22 October to 30 November 2025

We’ve held two rounds of non-statutory consultation on our proposals for the Morven Hawthorn Pit Grid Connection Project.

Between July and September 2024, we held a non-statutory consultation on broad corridors of search for where our offshore and onshore infrastructure within England could be located. We considered all feedback, undertook further technical studies and engaged with stakeholders to identify potential options for the offshore cable corridor, cable landfall, onshore cable corridor and land substation.

We then held a second round of non-statutory consultation on these options between October and November 2025. We are currently considering all feedback received and will continue engaging with stakeholders as we develop our proposals.

We plan to hold a further round of consultation in 2026 before submitting our DCO application.

You can view and download our consultation documents from the 2024 and 2025 consultations in the information hub below.

Morven Hawthorn Pit Grid Connection Project

2025 non-statutory consultation brochure

October 22, 2025

Morven Hawthorn Pit Grid Connection Project

2025 non-statutory consultation offshore cable corridor map

October 22, 2025

Morven Hawthorn Pit Grid Connection Project

2025 non-statutory consultation onshore corridor options map

October 22, 2025

Morven Hawthorn Pit Grid Connection Project

2025 non-statutory consultation land substation refined search areas map

October 22, 2025

Programme Document

Our programme document outlines our intended activities and timescales for the pre-application stage of the Morven Hawthorn Pit Grid Connection Project DCO application. We will update this document as we progress through the pre-application stage and upload the latest version to the information hub. 

MHPGC Programme Document

December 10, 2025

Information Hub

Offshore and onshore infrastructure in England

Documents relating to Environmental Impact Assessment, consultation and planning processes for the Morven Hawthorn Pit grid connection offshore and onshore infrastructure in England will be added here as the project progresses.

Morven Hawthorn Pit Grid Connection Project

Morven Hawthorn Pit grid connection scoping report

February 4, 2025

Morven Hawthorn Pit grid connection scoping report download

Offshore infrastructure in Scotland

Documents relating to Environmental Impact Assessment and planning processes for the Morven Hawthorn Pit grid connection offshore infrastructure in Scottish waters will be added here as the project progresses.

Morven Hawthorn Pit Grid Connection Project

Morven Hawthorn Pit grid connection scoping report

November 4, 2024

Morven Hawthorn Pit grid connection scoping report download